SLEMCO's Proposed Schedule of Events

Description Months from IRP Filing Expected Dates
SLEMCO submits request to initiate IRP
At filing date
March 2, 2026
SLEMCO files data assumptions and description of studies to be performed
1
April 2, 2026
SLEMCO holds first stakeholder meeting
2
May 14, 2026
Stakeholders may file written comments
4
July 14, 2026
SLEMCO publishes draft IRP Report
12
March 12, 2027
SLEMCO holds second stakeholder meeting
13
April 2, 2027
Stakeholders may file comments about draft IRP report
15
June 2, 2027
Staff files comments on draft IRP
16
July 2, 2027
Final IRP filed by SLEMCO
19
October 1, 2027
Stakeholders submit list of disputed issues and alternative recommendations
21
December 1, 2027
Staff submits recommendations to the Commission including whether or not a proceeding is necessary to resolve disputed issues
22
January 3, 2028
Commission order acknowledging IRP or sets hearing for disputed issues
24
March 2, 2028